Tuesday, August 13, 2013

NS Vikrant (2013)

Design[edit source | editbeta]

INS Vikrant is the first ship of the Vikrant-class of aircraft carriers. It is 262 metres (860 ft) long, 60 metres (200 ft) wide and displaces about 40,000 metric tons (39,000 long tons). It features a Short Take-Off But Arrested Recovery(STOBAR) configuration with a ski-jump. The deck is designed to enable aircraft such as the MiG-29K to operate from the carrier. It is expected to carry an air group of up to thirty aircraft, which will include up to 20 fixed-wing aircraft, primarily the Mikoyan MiG-29K and the naval variant of the HAL Tejas Mark 2, besides carrying 10 Kamov Ka-31 or Westland Sea King helicopters. The Ka-31 will fulfill the airborne early warning (AEW) role and the Sea King will provide anti-submarine warfare (ASW) capability.[3][4]

The Vikrant is powered by four General Electric LM2500+ gas turbines on two shafts, generating over 80MW of power. The gearboxes for the carriers were designed and supplied by Elecon Engineering.[2][5][6]

Construction[edit source | editbeta]

Construction was complicated due to difficulty in obtaining suitable AB/A grade steel, which Russia was unable to supply. To resolve this, the Defence Metallurgical Research Laboratory (DMRL) and Steel Authority of India Limited(SAIL) created facilities to manufacture the steel in India.[3] [2] Reportedly, three special steels are used on Vikrant, for the hull, flight deck and floor compartments which are manufactured at the Bhilai Steel Plant and Rourkela Steel Plant.[7]

The keel for Vikrant was laid by Defence Minister A.K. Antony at the Cochin Shipyard on 28 February 2009.[8][9] The ship uses modular construction, with 874 blocks joined together for the hull. By the time the keel was laid, 423 blocks weighing over 8,000 tons had been completed.[10] The construction plan called for the carrier to be launched in 2010, when it would displace some 20,000 tonnes, as a larger displacement could not be accommodated in the building bay. It was planned that after about a year’s development in the refit dock, the carrier would be launched when all the major components, including underwater systems, would be in place. Outfitting would then be carried out after launch. As per the Cabinet Committee on Security (CCS), sea trials were initially planned to commence in 2013, with the ship to be commissioned in 2014.[11][12]

In March 2011, it was reported that the project had been affected by the delay in the delivery of the main gearboxes for the carrier. The supplier, Elecon Engineering, attributed it to having to work around a number of technical complexities due to the length of the propulsion shafts.[13] Other issues resulting in delays included an accident with a diesel generator and an issue with its alignment.[14] In August 2011, the defence ministry reported to the Lok Sabha that 75% of the construction work for the hull of the lead carrier had been completed and the carrier would be first launched in December 2011, following which further works would be completed until commissioning.[15][16] On 29 December 2011, the completed hull of the carrier was first floated out of its dry dock at CSL, with its displacement at over 14,000 tonnes.[5] Interior works and fittings on the hull would be carried out until the second half of 2012, when it would again be dry-docked for integration with its propulsion and power generation systems.[1][2]

In July 2012, The Times of India reported that construction of Vikrant has been delayed by 3 years, and the ship would be ready for commissioning by 2017. Later, in November 2012, NDTV reported that cost of the aircraft carrier had increased and the delivery has been delayed by at least five years and is expected to be with the Indian Navy only after 2018 as against the scheduled date of delivery of 2014.[17] Work has begun for next stage which includes installation of the integrated propulsion system. Italian defence major Avio is installing the integrated platform management system (IPMS).[18][19]

Launch[edit source | editbeta]

In July 2013, defence minister A. K. Antony announced that the Vikrant would be launched on 12 August at the Cochin Shipyard. The ship was launched by his wife, Elizabeth Antony, on 12 August 2013. Extensive sea trials are expected to begin in 2016 and the ship will be inducted into the navy by late 2018.[20][21]

After the launch, Vikrant was re-docked for further work, including completion of the flight deck and installation of the bridge. According to Vice Admiral Robin Dhowan, about 83% of the fabrication work and 75% of the construction work was complete. He said that 90% of the body work of the aircraft carrier had been designed and made in India, about 50% of the propulsion system, and about 30% of its weaponry. He also said that the ship will be equipped with a long range missile system with multi-function radar and a close-in weapon system (CIWS).[20]

References

No comments:

Post a Comment